• Thursday, May 02, 2024
businessday logo

BusinessDay

Egbin Power 1320mw capacity attainment faces grid, distribution challenges

businessday-icon

The euphoria of Egbin power plant reaching full capacity of 1,329 megawatt (MW) thereby boasting power supply in the country is going to be short lived as industry sources said not all that is  generated can be sent out because of grid and distribution constraints.

This is despite the claims by the government that the national grid has the capacity to wheel 7,000MW.

Currently, the power plant is generating 1000 megawatts of electricity but it has not been able to send out more than 560 megawatts maximum thereby wasting the remaining capacity while several millions of Nigeria are in darkness.

 The 1,320 megawatts capacity plant will by tomorrow officially certified to have attain full generation capacity as all its six steam turbines with capacity of 220mw each are currently operating at full capacity. Steam turbine (ST-5) that has been down due to some technical problems is now fully rehabilitated and is up and running, a source close to the plant said.

Kola Adesina, chairman of Egbin Power told BusinessDay that the plant is ready to go full blast as it has what it takes to operate at full capacity for the benefits of Nigerians.

However in response to the  issue of  grid inability  to take the power generated, the Transmission Company of Nigeria, TCN blamed the problem on electricity distribution companies (Discos) for not having the capacity to pick  the loads generated by generating companies (Gencos).

Ndidi Mba, principal manager, TCN, said the issue of transmitting the power generated by the TCN is a function of the distribution companies. She said the TCN can only transport what the distribution companies can take, adding that doing anything to the contrary may destabilise the grid. According to her, what is taken out of the grid should be what is sent in from the generation plant for now.

“If the distribution companies can take 7000 mw we are ready to supply them. The grid has unutilised 2000mw which the government the eligible consumers to take,” she said.

She insisted that as matter of fact the TCN has capacity to wheel 714mw presently but that Discos did not have the capacity to receive more than 4000mw or a little above that.

However, industry analysts observed that transmission in the last 12 months experienced limitations in the value chain that precludes their ability to receive the consistent power supply that they have a right to expect.

Report indicates that the maximum wheeling capacity reached by Transmission Company of Nigeria has been 5,074.7 Megawatts, MW (attained February 2nd, 2016) versus its claims of increased capacity from 5,500 MW to 6,000 MW, wholly untested and unproven.

There is a planned target transmission capacity of 8,200Mw by 2018 and 10,000Mw by 2019. The transmission arm of the power supply value chain has been tagged the weakest link of the chain by operators. If the target planned works  are achieved, it would boost stable electricity supply.

Association of Nigeria Electricity Distribution (ANED) only recently attributed the poor state of the country’s power supply to the Transmission Company of Nigeria, TCN describing it as the weakest link in the power supply chain.

The association explained that “any plans by TCN to complete 22 critical projects captured in the 2016 budget has to be a function of the availability and release of the requisite funding required for same.

According to them “It is not clear that TCN has received, nor will it receive, any funding that comes close to enabling it complete the indicated projects –a continued legacy of limited and poor funding of a vital aspect of power infrastructure.”

They argue that considering the importance of power as the fundamental ingredient for the growth of any economy, getting all the parts to work in sync is crucial.

“Factually, a major contribution to the liquidity challenges that the DISCOs are currently experiencing is TCN’s infrastructure and technical limitations in wheeling power to the proper areas of a DISCO’s geographical footprint. “Also, DISCOs are currently experiencing a monthly loss in excess of N1 billion due to limited transmission capacities in various areas of the country. Analyst observed.

Sunday Olurotimi Oduntan, Executive Director, Research & Advocacy, Association of Nigeria Electricity Distribution was quoted to have said at a recent programme that a fundamental premise of the privatisation of the Power Holding Company of Nigeria, PHCN, successor companies was that TCN would be operated efficiently, consistent with private sector attributes of productivity and managerial efficiency

Meanwhile report emanating from the Power Advisory Team of the federal government indicates that average power sent out was 4,078.79MWh/hour down by142.37MWh/h from the previous day.

About 1,738.5MW was not generated due to unavailability of gas, 40MW not generated due to unavailability of transmission infrastructure, while 1,092.1MW was not generated due to high frequency resulting from unavailability of distribution infrastructure. Another 190MW was not generated due to water management.

The power sector lost an estimated N1,469,000,000 on April 25, 2018 due to insufficient gas supply, distribution infrastructure, transmission infrastructure and water reserves.

The dominant constraint  for that day remains gas – constraining a total of 1,738.5MW from being available on the grid.