Lessons for Nigeria as electric trains link Cairo to cities

Lessons for Nigeria as electric trains link Cairo to cities

With substantial progress made by the federal government at the various segments of the ongoing standard guage rail projects across the country like that of $ 1.5 billion Lagos-ibadan and Itakpe Warri standard gauge rail corridors, other countries in Africa such as Egypt is far ahead as the North African country is fast embracing the electrified system of passenger and cargo movement by rail.

Work was at advanced stage on the construction site for the railway tracks that will accommodate the electric train that will link Cairo to the new cities in Upper Egypt. This rolling stock will enter into service in October 2021, according to the forecasts of Kamel al-wazir, the Egyptian minister of transport.

This major mobility project executed by the China Civil Engineering Construction Corporation (CCECC) will require a total investment of 739 million dollars.

Read Also: Court restrains Abia electoral commission from conducting LG elections

The project is being financed via a loan from the Chinese government, in accordance with an agreement signed with the Egyptian authorities in September 2017.

Kamel al-wazir’s working visit last October was aimed at assessing the progress of work on the various sites of the project to build an electric train to link the new cities under construction in Upper Egypt and Cairo with 82 percent of work already completed at the level of drilling of the tunnels.

Construction of the maintenance workshop for the electric train is 60 percent complete while the project is 35 percent completed at the level of the construction of the railway bridges with 62 percent work done.

It is estimated that at the current rate of work, the first tests of the electric train can be carried out by August 2021. These tests will be carried out between Al-salam, the new administrative capital, and the 10th of Ramadan City, the new city under construction in the city of Sharqia .

The electric train will not be fully operational until October 2021. It will then link Cairo and the new cities under construction, including Obur, Mostakbal, Shorouk, the new Heliopolis, Badr, the Industrial Zone, 10th of Ramadan City and NAC. The railway line will be 90 km long with 16 stations. The future electric train built by China will have a capacity of 30,000 passengers and will be able to carry up to 500,000 people a day.