FEC approval of N169.74bn contracts for road construction nationwide to expand economy-Fashola

Babatunde Fashola

The Federal Executive Council has approved the award of N169.74 Billion contracts for the construction and rehabilitation of 10 roads across the country.

Babatunde Fashola,the Minister of Power, Works and Housing,confirmed in a statement on Sunday that the projects would enhance Federal Government’s objective of improving transportation infrastructure and restoring the nation’s road network as part of implementation of the Federal Government’s Economic Recovery and Growth Plan.

The approval,Fashola said was sequel to a memorandum presented to the Council by the Minister on May 2nd, 2019, covers the Rehabilitation of the Umuahia(Ikwuano)-Ikot Ekpene Road, Umuahia, Umudike in Abia State, Rehabilitation of Calabar-Oban-Ekang Road (Section1) in Cross River State, Construction of Yola-Fufore-Gurin Road in Adamawa State, Rehabilitation of Ado-Ekiti –Igede-Aramoko-Itawure Road in Ekiti State and Rehabilitation of Funtua-Dandume-Kaduna State Border Road in Katsina State.

Others, according to the memorandum, are the Rehabilitation of Makurdi-Gboko-Katsina-Ala Road (Yandev-Katsina-Ala Section) in Benue State, Rehabilitation of Old Enugu-Onitsha Road (Opi Junction-Ukehe-Okpatu-Aboh Udi-Oji to Anambra Border), Rehabilitation and Dualization of the 74KM (Approximately) Aba-Ikot Ekpene Road in Abia/Akwa Ibom States, Construction of 4 kilometre Township Road in Gaya Local Government Area of Kano State and Rehabilitation of Billiri-Filiya-Taraba State Border Road in Gombe State.

While the Umuahia (Ikwuano)-Ikot Ekpene Road is awarded to Messrs Hartland Nigeria Limited/ Raycon and Company Nigeria Limited in the sum of N13,296,283,958.68 with a completion date of 48 months, the Rehabilitation of Calabar-Oban-Ekang Road (Section1) in Cross River State is awarded to Messrs Setraco Nigeria Limited in the sum of N27,781,851,866.55 with a completion date of 24 months while the construction of Yola-Furore-Gurin Road (approximately 56KM) is awarded to Messrs Wiz China Worldwide Engineering Limited in the sum of N13,643,670,884.81 with a completion date of 12 months.

The Rehabilitation of Ado-Ekiti–Igede-Aramoko-Itawure Road in Ekiti State (35KM approximately), according to the memorandum, is awarded to Messrs Deux Projects Limited/Hitech Construction Company Limited at N14,838,220,269.00 with a completion period of 30 months, while the Rehabilitation of Funtua-Dandume-Kaduna State Border Road in Katsina State is awarded to Messrs Rabash Enterprises Nigeria Limited/Afdin Construction Limited in the sum of N9,887,040,586.50 with a completion period of 24 months.

Also while 200-250 workers will be employed in the rehabilitation of Ado-Ekiti –Igede-Aramoko-Itawure Road in Ekiti State with 90 per cent of the jobs to be handled by Nigerians and 10 per cent by expatriates, the rehabilitation of Funtua-Dandume-Kaduna State Border Road in Katsina State will generate 200 jobs with 80 per cent for Nigerians and 20 per cent for expatriates.

While itemizing the Scope of Works to be covered in each of the Projects, the Minister also gave extensive details of the procurement processes which began under the 2018 Appropriation with newspaper advertisements in July 2018 and culminated in the certification and issuance of a Due Process Certificate of “ No Objection” for each of the 10 Projects by the Bureau of Public Procurement (BPP).

 

‎HARRISON EDEH,ABUJA‎